The
daily feedback loop
by
Arne Oas
So,
now you’ve gotten to the point where the first set of work orders
have been assigned and passed out to your staff. It’s the
responsibility of the worker’s immediate supervisor to ensure that
the assigned work is being accomplished. If there is any deviation to
the plan, it will be that supervisor who approves the change to the
schedule.
The
technicians perform the work. What do you do when the techs turn in
those work orders?
At
the end of each shift, the supervisor needs to collect all the
completed work orders. Starting with one clipboard (I prefer that each
person has his or her own), remove all of the work orders. If you have
planned properly, clip the next day’s scheduled work on the
clipboard for distribution the next day. Rapidly review the work
orders for the work that was completed that day. If you use electronic
work orders or if the workers are doing entry, you still need to
perform this review to ensure proper documentation of work exists in
the system.
Review
the work orders for the following information:
A)
The date that the work was accomplished.
B)
The initials of the person(s) that worked on the job.
C)
The amount of time the person(s) took to work on the job.
D)
The failure code stating the reason for the work.
E)
The solution code describing what fix was performed.
F)
The parts used and the quantity of parts used. (Only the part number
and quantity need to be documented for any item used.)
G)
Any work orders not completed.
Review
the work orders for suggested changes and indicate those that are
approved. Approval here will allow data entry to go ahead and make the
change. Approval can be as simple as the supervisor initialing the
request.
Review
the work orders for new work or problems based on notes of defects or
conditions. Slash (draw a line) through all notes or problems to
indicate to data entry that the notes have been reviewed and the
necessary follow-up action started. Slashing the note provides a
double-check function through data entry. If they don’t see a slash,
they can route the work order back to the appropriate supervisor for
action. Proceed to the next person (clipboard) and perform the same
steps. Forward all the reviewed work orders to data entry.
After
that step, meet with the next shift’s supervisors. Pass on critical
jobs that must be completed and brief them about any ongoing work.
Data
entry personnel should receive all the preventive maintenance (PM) and
repair work orders from the responsible person. After collecting all
the previously assigned work orders, they should divide them into five
groups. They should sort the groups as follows:
1)
Blank PM work orders — those that are not completed
2)
Clean PM work orders — those with only time and labor
updates
3)
Dirty PM work orders — those with notes or changes
4)
Scheduled repair work orders
5)
Emergency repair work orders
The
work orders are sorted into these five groups for ease of entry into
the computer system. Each group requires different information and
actions. The work should then be entered (completed) in the computer.
Make
any authorized changes. Return questionable items to the supervisor.
File the work orders and hold them for a minimum of four weeks to
allow for possible software problems that may necessitate work
re-entry. Where required, file special regulatory work orders in their
appropriate locations.
At
the end of the day, print, distribute and review the following CMMS
reports:
Work
accomplishment (reports the time of the previous day’s work): Review
this report to check for large variances between the time to
accomplish the work and the estimated time. Investigate any large
variances.
Completed
work list: Distribute this to the maintenance and operations foremen
and supervisors in order to inform them of accomplished work.
Work
order backlog list: Update this daily and distribute it to all
maintenance and operations foremen and supervisors to inform them of
the work still outstanding or open.
This
is the daily feedback loop that will allow the supervisor to monitor
and control the work. E-mail me with any questions or concerns that
you may have about this topic.
Arne
Oas is the senior consultant for Computerized Facility Integration. He
can be reached at 215-918-2165 or by e-mailing aoas@gocfi.com.
This article appeared in the October/November 2004 issue of MRO Today
magazine. Copyright 2004.