Controlling
your backlog
by Arne Oas
Work orders are
getting lost in the system. Work isn’t accomplished or completed.
The backlog is growing and out of control.
Sound familiar?
To reduce overall
maintenance cost and improve work order execution, it’s necessary
for maintenance supervision to learn how to schedule the workload.
Proper scheduling requires the establishment and control of a
maintenance backlog.
Within the
maintenance work order system, when a person notes a problem or wants
work done, it goes into the maintenance system as a Work
Request and is assigned a work order number. Requests are
reviewed for approval and either expedited, if an emergency, or held
for scheduling, if a non-emergency. Approved, non-emergency requests
need work requirements developed, so the work is moved to a planning
queue. Once planned, the queued work becomes the backlog. This is then
the record of requested jobs approved to be worked on. They are
planned but not yet scheduled.
The backlog is the
heart of efficient workforce utilization because it’s the primary
means used in balancing requested or required work with the available
workforce. The correct allocation of personnel to required work areas
is essential if prompt response and proper management of maintenance
resources is to occur.
Use priorities within
the work order system, availability of parts and personnel, and
equipment criticality to determine when and which work will be
performed.
Backlog size is also
critical to perform effective scheduling. Too small of a backlog does
not provide enough of a work cushion to allow for smooth scheduling;
it can cause personnel transfers or layoffs. Too large of an equipment
backlog may give the requester a feeling that the work never will be
done (that’s usually true). Therefore, the scheduling team must
monitor the backlog size by total hours of estimated work divided by
total available weekly labor hours. For most facilities, strive for a
backlog greater than two weeks but less than five weeks. If backlogged
work is outside these limits (longer than five weeks), consider
solutions such as contract work, overtime or job cancellation.
Re-evaluate any job (and priority) in the backlog for more than one
year.
Proper control and
scheduling of this work order backlog is fundamental to successful
maintenance operations. To assist in this control, develop a Backlog
Report. The report should contain the work order number, the
equipment (location) identifier, equipment (location) name, Relative
Importance Factor (RIF), a brief description of the problem or work to
be performed, type or skill of the personnel required to complete the
work, the time required to complete the work and the work order status
(in planning, awaiting parts, ready, open).
Print and distribute
a copy of the report weekly to the planning and scheduling team. This
team should consist of production (operations) and maintenance
personnel. Individual team members should review the backlog (both PM
and repair) and determine if unusual parts or special scheduling is
needed to complete the work. They should note these requirements on
the report. The entire team should review the backlog weekly in a
group setting. The individuals who actually schedule performance of
the work on a master report should note combined information about
equipment availability and special parts orders.
A sample agenda for
the meeting is as follows:
A) Planning issues
(10 minutes)
B) Backlog status
review (5 minutes)
- Number of total
jobs
- Jobs waiting on
planning
- Jobs waiting on
parts
- Jobs ready to
schedule
C) Priority issues
(15 minutes)
D) Backlog size and
required action (10 minutes)
E) Review work status
(15 minutes)
F) Review shutdown
schedule (10 minutes)
In the meeting,
remember that work should only be scheduled if the parts, manpower and
equipment are available. Also, utilize some kind of an importance
evaluation scale to schedule the work.
After the meeting,
assign someone to schedule jobs for either people or crews. Start
scheduling by dividing the work among the people/crews available for
the following week. Base this assignment on the work shown, the
equipment or location, the access required for the work and the
knowledge of personnel/crew capabilities. Note any special
instructions on the individual work order (parts, times, scheduling
constraints, etc.). After completely assigning the work, review the
workload for each person or crew to ensure they aren’t overloaded
and that there is proper distribution.
For a helpful hint,
many find it easier to write down the amount of hours usually
scheduled for an individual. Some people will get more planned work
because of their ability or skill level, while others can expect less
planned work because they may be used for troubleshooting. Fill the
remaining time with bench work, short entry/exit jobs or older work
from the backlog.
Working with one
person’s/crew’s workload, the scheduler (usually the direct
supervisor at this point) divides the person’s work into the days of
the week. Schedule important work for the beginning of the week to
ensure its completion. Where any work order has a day or time
indicated, schedule it accordingly. Check the distribution to ensure
no single day is overloaded and make necessary adjustments.
If you use paper work
orders, clip each day’s work together and note the person/crew on
the top work order. If you use a computer, flag them in the manner
required by the CMMS. This often involves assigning personnel and
creating targeted start dates on each CMMS work order.
Repeat the above
steps for each remaining person or crew requiring scheduling.
When finished, set
aside the work orders for distribution during the following week.
Maintenance personnel should distribute and receive work orders on a
daily basis. The supervisor reviews them daily and makes any required
scheduling or reassignment adjustments. This daily feedback and
scheduling loop allows the supervisor to monitor and control both work
performance and the backlog. This relieves the chaos and controls the
work. s
Arne
Oas is the senior consultant for Computerized Facility Integration. He
can be reached at 215-918-2165 or by e-mailing aoas@gocfi.com.
This
article appeared in the June/July 2004 issue of MRO
Today magazine. Copyright 2004.
Back to top
Back to MRO Coach archives
|