|
More
improvement?
Yes, things can get better!
Here are 10 steps to creating a new flow.
by
Mark Gooch
I was walking through
one of our plants a couple months back and saw work cells that had
completed a lot of transformation work (a one-week focused Kaizen
Blitz, co-located work centers and inventory, “leveled” work
groups/teams across shifts, etc.), yet it looked like there was more
that could be gained. I have had that question asked of me many
times, “Is there more opportunity in an area where we have already
‘completed’ a Kaizen Week?” The answer is YES! In fact, many times
the greatest improvement is yet to come.
Very often, the first
pass event or activity actually prepares a cell and work team for
improvement. Often, the cell has not had any form of standard work
applied until the first event week is completed. Second, a favorite
saying of mine begins to take shape: “You never know how much you do
not know until you know!” In other words, what do you look for when
you aren’t sure what you are looking for?
To illustrate this, let
me give you a detailed example of one cell I worked with in the past
three months and the additional things we found.
Cell details/data:
A cell with five people on the work team, and three shifts of work
equals 15 total people. The lead time of a part starting new in the
product flow would complete in 36 hours. Inventory turns in the cell
(WIP) was four days. Approximately 1,800 square feet of floor space
was being used. On the surface, not bad numbers, until we looked at
the key metric, Takt time for the cell, and realized everything was
severely distorted! Here’s what we found.
Takt time for the cell
was 16 seconds. The summation of individual work station cycle times
was 45 seconds. The quick formula for minimal staffing is the sum of
the cycle times divided by Takt time. In this case, we needed 2.8
people per shift — we had five. When the leadership team watched the
activities in the cell and monitored what everyone was doing they
found that all employees were busy 100 percent of the time, so the
formula had to be incorrect, right? WRONG! Four of the five people
were over-producing 100 percent of the time. Inventory was stacked
up between each work center and the team members were actually
batching and pushing batches of inventory from one work center to
the other. The fifth person was running from station to station
helping to “expedite” parts, aligning parts for packaging, moving
“large” skids of parts from one work center to another, usually out
of the cell first, then back in later, and so forth.
After four hours of
watching the flow of the product, collecting multiple time
observations to get good, consistent information, counting inventory
counts and seeing which workstations demanded attention and which
ones could be “loaded” to let the machine do its job and then unload
or let the machine discharge itself, we went to a conference room
with a couple of the cell members and the team leaders to lay out
the new flow.
Creating a new flow
1. The first thing we did was eliminate all “storage” areas
between work centers. We moved the equipment as close together as we
could possibly get it without creating an unsafe position.
2. We set all material to be “charged” from outside of the
cell — never interrupt the flow of material or work when moving
material into the cell!
3. If a machine could unload itself we provided plastic (PVC)
shoots or tubes to direct the material to the loading surface of the
next work center. If the machine had to be unloaded manually, we
modified the unload mechanism to be a very “light” touch device.
Most of this was accomplished with springs, levers and quick clamps.
4. None of the work centers required more than eight or nine
seconds of processing time and just two required someone to be by
the equipment during the total processing time. Therefore we created
a movement path for the operators to move with the part, escorting
it from center to center if the machine did not unload it to the
next center on its own. In other words, the employees’ natural
walking from station to station became the material movement
mechanism.
5. All inventory inside the process was completed, then
removed from the cell. No additional inventory was produced until we
were ready to resume production. This by itself made more than 450
square feet of floor space available.
6. We divided all production activity into two flow paths and
removed material support and one subassembly process from the cell
flow. This material support and subassembly work was given to a
third person located outside the cell and next to the work station
requiring the subassemblies.
We also discovered that the subassembly required a 60 minute curing
activity so a batch size was developed — a 60 minute batch. We
created a buffer quantity of one batch that the cell used with one
batch in reserve, hence a two-bin system of inventory control. When
the first bin was completed and the second bin became the “use” bin,
the third person in the cell immediately produced a new bin of
subassemblies.
This process took less than 10 minutes. Placing the parts in a
position that FIFO was used to remove the subassemblies, the 60
minute cure time was met, inventory never ran out and the max amount
of inventory at the work center never exceeded two hours’ worth.
(Compare that to the four days of inventory prior to the event.)
7. We created single piece flow, continuous of product. No
work center produced more than Takt time, and all parts were moved
from center to center by the operator or the machine itself.
8. After three hours of realignment, we started the cell back
into production, with 2.5 people per shift not 5. In other words, a
50 percent productivity improvement. Our results were “amazing” to
everyone involved, including the operators. The two operator’s flow
paths were each 16 seconds. The “.5” person’s material support and
subassembly activity was eight seconds, and within the actual cell
production activity, therefore it did not impact lead time of the
product. With that in mind, after three days of production, our new
lead time, from start of new part until in a box and ready to ship
was 32 seconds compared to the 36 hours (a greater than 99 percent
improvement!). Internal WIP was 12 pieces of inventory compared to
four days’ worth before we started.
9. What do you do with a “.5” person in a cell?
If that person never leaves the cell, you really have 1 person not
.5. So, we aligned a second cell next to the cell we worked with and
moved similar material support work from the cell’s work content and
used the second half of the .5 person in the second cell — true
improvement for both cells.
10. The final metric we saw improved was the combined cycle
times. Remember, prior to our changes it was 45 seconds. After our
changes it dropped to 40 seconds; an 11.1 percent improvement. How?
Remember our work in letting the machines unload parts when they
could and having the people remove and move the parts as they walked
to the next work center? Those two actions reduced the five seconds.
And there’s more to
come
And we accomplished all this in four hours of observation, three
hours of data analysis, three hours of cell realignment and one day
of observing and tweaking the process in the new flow.
So, was there more
improvement after one event? Well, the data says it was nothing
short of amazing. The best thing was that we identified seven
actions to reduce another 10 to 12 seconds of processing time, a 25
to 30 percent additional productivity opportunity, and we did not
even deal with raw material inventory.
Do you think we should
have another event?
The journey is not easy,
but it is absolutely exciting and never dull. Drop me a line or note
and let me know how your journey is going:
mark.gooch@pentair.com.
Mark is vice
president of Lean enterprise for Pentair Inc. He has held senior
level positions with GE Aircraft Engines, Goodrich Aerospace and
Williams-International and has worked with operations from 15 people
to organizations of 30,000. Contact Coach Gooch at 763-843-9866;
E-mail: markgooch@juno.com.
This article appeared in the
October/November 2006 issue of MRO Today magazine. Copyright
2006.
Back to top
Back to MRO Coach archives
|