|
Lean transformations
Are you using the basics?
by Mark Gooch
I spoke recently at an annual convention of
manufacturers. The topic was “Taking Lean to the Next Level.”
After my presentation a small business owner approached me and
with the greeting, “I am disappointed in your presentation. You gave
me nothing new to work with and everything you focused on doesn’t
even help companies like mine.”
I asked him to explain his situation and offered
some personal focus time. As he spoke, several things became apparent.
He had been to courses, workshops and conferences and read a few
books, but had never committed to learning or applying the basic
tenants or principles of Lean.
When we talked about identifying waste in his
system, he recounted the actions he had taken over the years to assure
waste never entered his business. When I asked about TAKT time, his
recoil was “That doesn’t apply to our company. We are a custom
design manufacturing business and you can’t use that automotive
stuff in my plant.”
I soon learned Mr. Disappointed’s idea of
overproduction and excess inventory (specifically WIP – work in
process) was focused just on the shop floor. He had indeed reduced
manufacturing cycle time (chip cutting and some assembly work) quite
impressively over the years, but he had never looked at engineering,
CNC programming, purchasing, quality or other functions that supported
the manufacturing area (shop floor). When he spoke of a three- to
four-week cycle time, he ignored the 15 to 18 weeks that jobs spent in
the previously mentioned areas.
As we spoke, I gathered some of the following
information and began applying the Lean techniques. His major and most
expensive area for inventory was in billable engineering hours
required and sold for design, layout and machine tool programming.
This became WIP in the purest sense, but was not considered such by
the business owner since it was not “traditional.”
The average job entered his process within two days of
receiving an order, and the initial design work was completed within
the first week of cycle time.
The job then waited in a second queue more than 30
days before it moved to the next process in another building where
part layout and final dimensioning was completed in one to two days.
Week 10 began the programming activities, which were usually final in
one day. At this point, more than 30 hours of labor were “tied up”
in billable hours, 11 weeks were gone and no invoicing had completed.
A scheduler was hired in the engineering group
(disguised as an engineering administrator) to log jobs, track open
jobs through engineering and schedule jobs for the next level of
activity.
All of this was over-production — 30 hours (less
than 4 days of work) had been accomplished but the complete cycle time
was now in excess of 11 weeks! Approximately
five percent of the cycle time was value added, leaving 95 percent as
non-value added to the customer or the business owner — the only
entity that had experienced any cash flow was the negative impact the
business owner had experienced.
When purchasing received the job, they usually
ordered the material the same day, since they were now being pushed by
the owner to “get that material in here immediately.” (After being
invited to work with this company for several months, I discovered
that a premium was paid 30 percent of the time to expedite material
delivery, something that could have easily been avoided by having the
design person order the material when it was specified 10 weeks
earlier.)
This can be classified as processing (or
over-processing) waste since expediting is seldom necessary. The
“need” was created by internal delays in getting the job
completed. It was an under-utilization of talent: the design person
was completely willing and able to place the order.
Weeks 12 to 14 were usually waiting days since the
material was on order. Week 15 began the actual manufacturing of the
average order. Even with the focus that had been placed on the
manufacturing process over the years, there was still opportunity.
Approximately three hours of manufacturing was required, yet it took
three weeks to accomplish the task.
Was there opportunity for this company?
Could they apply the tools of Lean to their business even
though they were “unique?” Was
there a way for them to improve on-time delivery, reduce operating
costs, improve cash flow, gain more business by reducing cycle time
and pricing . . . ? Use
the tools and make your own decision.
Mark
Gooch has held senior level positions with GE Aircraft Engines,
Goodrich Aerospace and Williams-International. He has worked with operations
ranging from 15 people to organizations of 30,000. Contact Coach Gooch
at 641-620-1320; E-mail: mgooch@simpler.com.
This article appeared in the
August/September 2005 issue of MRO Today magazine. Copyright 2005.
Back to top
Back to MRO Coach archives
|