|
Time
to spare
by R.T. “Chris” Christensen
Here’s a system for
answering the question, “We’re doing all this extra stuff to become
Lean, but where do we get the time to do it?”
We all hear the same line
from people working on lean projects. “When will we have the time to get
our work done? We are so busy now doing our job that if we stop and do a
Lean project, we will fall behind in our day to day work.” And I agree
with you that this will happen unless you plan ahead and take steps
necessary to make sure that all gets done.
That said, I also hear the
statement, “If I work hard and simplify my job, then I will work myself
out of a job and be laid off. My company says it needs to do this so
they can realize the savings my Lean initiative has generated.”
These two questions go hand
in hand. I have dealt with them in the shop, in the office, in union
shops and in non-union shops. Why should I work harder and put in more
time only to work myself out of a job? Doesn’t make any sense. The
question is always the same and the answer is basically the same, too.
The first things that
everyone in the company including the top management need to understand
is that we all want and need to work smarter and not just harder, and
that Lean is not another program to lay off workers and save money on
labor. A good Lean program isn’t about efficiency and productivity
alone. It is about improving the processes of the corporation and
reducing costs. Over the years, we have continually pushed the worker to
work harder and faster to reduce costs. And we have pushed to a point of
failure.
Faster makes more mistakes
and takes a toll on the worker. The standard pace for a worker, 3 mph,
was set up 100 years ago by Frank and Lillian Gilbreath, the husband and
wife team that started work standards and the concepts of industrial
engineering. As humans, we have not evolved at all since then, so to
continually push to work harder and faster than 3 mph is beyond human
capability.
In general, direct labor in
most companies is about 8 percent of the cost of finished goods. So,
even if you get a 10 percent improvement in labor, it is really only a
10 percent increase in an 8 percent component of your cost structure.
That’s a lot of effort for 0.8 percent improvement. Therefore, what we
need to do is work smarter.
If we work smarter, we can
generate tremendous cost savings that add up to significant savings for
the company. Working smarter means elevating everyone’s job, which is
the main objective of Lean. Lean forges the team that will lead the
company to successes.
To get started — and for a
short period of time — we will need to work more hours and spend more
time on the job to get the Lean ball rolling. Yup, you are going to do
more, but for a short period of time. I see so many companies start off
by saying they are going to do 5-S, or do SMED, or do Poka-Yoke, or
change to cellular manufacturing, only to end up with nothing after
years of toil. They have not identified cost points and where
value-added tools can work. All they do is continue to work long hours
doing their jobs and doing Lean. And nothing gets done.
What needs to be done is to
find out where the tools of Lean need to be employed to get the savings.
Just shining up a dirty machine is not 5-S, because if the dirty machine
wasn’t a key cog in the process, nothing makes it to the bottom line by
just cleaning it. What needs to be done first is to look at what the
process is and what it is that the customer is willing to pay for.
That tool is the Value
Stream Map. This is where you start. It might take three or four or five
days to get a good map of the process done, and it will require some
extra effort on the part of the people. But this is a very short-term
surge in the work effort. On one Lean mapping process I did, we had
people come in at 3 a.m. and get things running, spend 6 hours working
on the map and then spend another two hours or so back at their jobs.
That week, we put in about 60 hours, but the map got done and the plant
kept going. This is where the initial long hours are put in.
Then we analyzed the map. We
could see the bottlenecks where an application of the Lean tools would
get measurable savings. We then looked at what tools from the Lean tool
box were needed to get the job done and earmarked them for the process
improvement we were seeking.
Then we looked at what we
called the “Don’t Do Its.” This is the key to getting started on your
Lean journey. Don’t Do Its are things you do in the process that don’t
add a value to the product and that the customer will not pay for. The
solution is to just stop doing these things. Let me explain.
We were looking at one
company that had 156 steps in the process for one component of their
product. Unfortunately only eight of the steps were value-added — things
like forming, welding, grinding, assembly, priming, sanding, painting
and shipping. The other steps were things like moving to another
building, moving to yet another building, sorting, inspecting, moving
again and so on.
The process steps here were:
shipping, receiving inspection, move into the warehouse, put away, enter
into inventory system, cut the shipping documents, get parts, move to
loading dock, place on truck and ship it again — 11 steps, all non-value
added. The question here was, “Why didn’t you just put it in the second
building in the first place and save all that time and energy?” Just
don’t do that any more.
It’s a classic “Don’t Do
It.” This is how you get the time to do Lean. Go through your value
stream map, identify the “Don’t do Its” and just get rid of them. This
is how, after a short burst of energy, you free up wasted process time
that is now available for streamlining value added portions of the
business. You have spent a little time up front to get things going and
gotten rid of the simple stuff that wasted your time.
Now you have the time for
more complex Lean tasks. You have already reduced costs for the company
and shortened process time and freed up space: these are the savings.
Now you utilize the kaizen blitz process to implement Lean Tools in
other value added processes that the value stream map identified. You
are now working smarter — not harder — and costs are again coming down.
One company I worked with
added another $50 million in annual sales with the same staff and
equipment. And they were still working eight hour shifts five days a
week. They had worked that 60-hour-week, got rid of the Don’t Do Its and
made some good Lean progress in about four months. They got the
efficiencies needed to take on some new work.
As Tom Peters says, “I am
still looking for the company that has downsized for success.”
We are not talking about
short-term profit taking by reducing headcount; we are taking about the
big picture and growing the company. I just gave you the implementation
plan to do that, so go do it. Get that value stream map defined. And get
rid of the Don’t Do Its.
R.T. “Chris” Christensen
is Emeritus Faculty at the University of Wisconsin, Madison, and is
Emeritus Director of Operations and Maintenance Management Certificate
Programs at the Universities Executive Education Department in the
School of Business. Contact Coach Christensen at 262-613-0073
E-mail:
crchristensen1958@wi.rr.com.
This article appeared in the
April/May 2007 issue of MRO Today magazine.
Copyright 2007.
Back
to top
Back to MRO Coach archives
|