The
keys to good planning
by R.T. “Chris” Christensen
It
comes up time and again. How can you possibly schedule a maintenance
department with all the emergencies and special work orders that
we’re always called on to do? Maintenance is chaos, and there is no
way to plan out of it, right? You can if you begin to understand
several key points.
In
scheduling, all you really do is allocate time. It’s time
management. Time is the only commodity that goes away by itself. The
clock keeps ticking, whether you use it or not. Waste an afternoon and
tomorrow the tasks that didn’t get done still await you. The machine
is still broken. The supervisors are still waiting for you to fix the
machine. You still have the parts (you read my past columns, right?).
Everything is still here, right where you left it, except one thing.
The time to do the work is gone and there are new pressing problems.
The work keeps piling up. How do you get out of this situation?
Remember,
scheduling is simply an allocation of time. You must start allocating
time to schedule the operation. This is called planning, and a couple
of basics are required.
The
first thing you need to do is determine how much time is available
each day by craft and then multiply that times the number of days you
plan to work in a week. No, there isn’t eight hours available in a
day. At best, there’s only seven hours available per day when you
subtract two 10-minute breaks, a half-hour lunch and two five-minute
wash periods. Your department’s time might be different than this,
so use your figure when calculating this.
Next,
determine how much time it’s going to take to get each task done.
This will include time allocation for things like travel, inspection,
research, parts location, tools acquisition, coffee breaks, talking to
Jim about last night’s game, whatever. Now, it’s a simple task to
load the days up with the time estimates based on the hours available.
This sets a basic schedule.
Simple,
right? But, consider this. To assist in scheduling the shop, you might
want to break your work orders down into four types:
1)
Priority work orders
2)
Non-critical work orders
3)
Preventive maintenance
4)
Emergency work orders
What
you begin to do is to look at the amounts of time that you spend each
day doing work that falls into these areas. You then will begin to see
a pattern in how much of your day is spent working on PMs,
emergencies, and critical and non-critical work orders.
You
can now build the schedule. Start with the easy one first, then the
critical jobs and then finally schedule the fillers.
First,
sequence the required time each day for PMs and allocate the work
needed to be done into the time available. If you find that 20 percent
of your daily time is spent on preventive maintenance, then sequence
PM work orders that take up 20 percent of the day. Next, lay the
priority work orders into the schedule. These are usually big jobs
that you need to get done, so here is where you allocate time to
complete them. See if there is enough time to get the jobs done by the
date they are due. But in this category, start with the bottleneck
machines first.
Here
comes the tricky part. After doing all this, you begin to understand
how much of the time is spent each day and what needs to be done to
meet the due dates. The next jobs to schedule are emergency orders.
You don’t know what they are, but you have an understanding of the
time spent each day on such orders. So, allocate some time in your
schedule based on past averages to work on emergencies. We call these
unplanned orders, but what you are doing is setting time aside for
them and, in effect, planning for the unplanned.
This
leaves the non-critical work orders. They get scheduled last and fit
into the time available. Schedule them last as this is where you get
added time if you have a more or less than average amount of emergency
work to do. If things run to schedule, you complete the PMs and
planned work orders, schedule the emergency time and finish the
non-critical jobs, too. If there is time left, you can pull forward
additional hours of non-critical work. But if disaster strikes, you
can reschedule the non-criticals to get more time for the emergency.
Because these are non-critical work orders, a week or two early or
late won’t make much difference.
This
is a great way to schedule the operation. Do this and you’ll find
that things start getting done. When that happens, the amount of
emergency work will, in fact, go down. Planning sequence is the key to
successful scheduling.
R.T.
"Chris" Christensen is the director of the University of
Wisconsin School of Business' operations management program. If you
have a question, contact Coach Christensen by phone at 608-441-7326 or
e-mail cchristensen@execed.bus.wisc.edu.
This
article appeared in the February/March 2005 issue of
MRO Today
magazine. Copyright 2005.Back to top
Back to MRO Coach archives
|