The specialty chemical manufacturer spent 90
percent of its purchasing dollars ($800 million a year) on raw materials and gave the
category practically all its buying attention.
It was a shining example of efficiency, says
Michael Fernandez, Witcos purchasing manager for its southern United States plants.
Maintenance, repair, operations and production materials
received the Cinderella treatment. MRO was the unappreciated stepchild.
MRO sat on the side, untouched, says
Fernandez. Nobody paid any attention to it.
Witco, however, was paying.
We spent $40 million a year on MRO and got no bang
for our buck, says Fernandez. We were wasting money and
opportunities.
For MRO goods across the companys 11 U.S. plants,
there was:
no standardized purchasing practices and procedures
no standardized products
no strategic alliances
no consistency in prices
thousands of suppliers
countless purchase orders
countless invoices
Each facility did whatever it wanted. We bought from
everybody, says Fernandez. The entire process was manual, and there was
no history available. We could tell how much we spent with a supplier, but not what
was purchased.
MRO needed a champion, a Fairy Godmother. It needed to
bring structure and notice to this area.
It was a total failure, says Fernandez.
According to Fernandez, five issues scuttled the program:
1) the integrators lack of knowledge on products not related to its core competency;
2) the loss of communication with suppliers for technical advice;
3) higher material costs;
4) longer deliveries; and,
5) improper substitutions.
They bought from whomever they wanted, he
says. We lost all contact with our suppliers.
Issues 3 and 4 were intertwined with consolidated delivery.
One of their suppliers was next door to us, but
hed drive 30 miles to deliver to the integrator, who then consolidated it with other
stuff and brought it to the plant, he says. It never made sense. So we
scrapped the idea (in 1996).
Learning from mistakes
Some companies swear off integrated supply when it fails. Witco saw failure as a learning
experience and tried again.
Bruce told us the only way were going to find
what works is to keep it at, says Fernandez. We learned the vertical approach
(one supplier bringing in all product groups) didnt work for us.
Davis put Fernandez in charge of finding a new integrated
supply solution not only for Taft, Gretna, Harahan and Memphis, but also for its seven
other U.S. sites.
The end result, rolled out in late 1996, took a
horizontal approach, with one supplier for each of five key product groups and
a team handling a sixth group.
For 10 of the 11 sites, Affiliated Distributors members
handle the main groupings. The lineup has Briggs-Weaver (mill supplies for nine
sites), Drago Supply Co. (mill supplies for one site), Red Man Pipe and Supply (PVF),
Warren Electric (electrical), Quality Bolt and Screw (fasteners) and Boise Cascade (office
supplies). Briggs-Weaver and Drago handle non-specialty safety products for their
sites and Vallen Safety supplies specialty items.
Using that core group for multiple sites allows Witco to
standardize products, buy more effectively and drive costs down.
(The safety setup) gives us the best of both
worlds, says Taft safety manager Ron Gros.
Witco saves money by adding commodity type
safety products (eyewear, gloves, hard hats, suits, etc.) to general mill supplies.
It gets peace of mind by having Vallen handle specialized, highly technical products
(escape packs, breathing lines, monitoring equipment).
The Sistersville, W.Va., site uses members of the
International Supply Consortium, since A-D does not have a presence in that area.
If an item falls outside these distributors
offerings, Fernandez uses traditional sourcing methods.
We do have some secondary suppliers, he
says. We tell our integrators, If you cant supply it, just tell
us. Well get it.
Fernandez says the new plan provides eight main pluses:
1) suppliers deal with their core competency;
2) lower prices due to pre-negotiated markups;
3) direct communication with suppliers;
4) scheduled deliveries;
5) savings incentives;
6) on-time delivery incentives;
7) vendor-managed inventory;
8) consigned inventory.
Working off a cost-plus arrangement (Item 2), we saw
our prices drop 15 percent, he adds. You have a lot of unknowns with a
discount arrangement. We learned that. You get 20 percent off list price, but
you dont know how much margin is in that list price.
Regarding items 5 and 6, Witco expects suppliers to provide
5 percent cost savings and 95 percent on-time delivery each year. If a supplier
surpasses both levels, it receives 25 percent of the cost savings that occur after the
initial 5 percent. If a supplier fails to meet the standards, it pays a penalty.
Making history
Eliminating the manual purchasing systems was also key. In 1997, Witco took the
first step by implementing Affiliated Distributors A-D Edge software.
45 steps, $70.76 to
process a Witco purchase order
Two years ago, Witcos accounting and finance departments found it cost $70.76 to
process each purchase order. They reached that figure by following a purchase order
through the company's 45-step process.
Each step was listed and affixed a cost figure. What follows is the breakdown of the
process:
Witco identified 20 process steps, ranging from searching for the product in a
catalog and completing a requisition to sourcing suppliers and placing the order to
receiving the product and delivering it to the user. Total cost: $54.70.
It also found four document matching and approval steps ($1.43), seven
invoice problem resolution steps ($7.45), three work exception
reports steps ($0.34) and 11 other cost steps ($6.84).
The company is working to remove steps and cut costs through the use of procurement cards
and the planned use of EDI and Internet procurement.
To reduce purchase order volume, proposed orders are held in a computerized queue and
grouped with other orders. At Taft, this eliminates 20 purchase orders a week (1,040
a year), triggering a $74,000 annual savings. |
For the first time, the company saw not only how much
it spent with suppliers, but what it actually bought. It also started to give the
company a true history of MRO product usage. The software was a temporary solution.
In the spring of 1998, Witco began full-scale installation
of SAP integrated business software. It will complete the massive undertaking in
late September and go live with the system on Oct. 1.
SAP will cover everything purchasing,
accounting, production, assets, building materials, maintenance, says Fernandez.
With SAP, Witco plans to utilize electronic data
interchange (EDI) for 80 percent of purchases. It currently does not use EDI.
EDI usage could save big money by reducing the cost of
processing a purchase order. It currently costs $70.76 to process such an
order. A reduction of even $11 would save Witco more than $1 million a year.
By embracing MRO, Witco spends less and gets noticed.
Before, we benchmarked everyone, says
Fernandez. Now, people call us and ask about our concept.
This article appeared in the August/September 1999 issue
of MRO Today magazine. Copyright 1999.
For more info on Witco, see "0.2 turns per year"
Back to top