|
A
tale of TPM
What do you do
when increased customer demand conflicts with maintenance needs?
Spacesaver Corporation turned to total productive maintenance.
by Paul V. Arnold
“It’s
fine to celebrate success, but it is more important to heed the
lessons of failure. How a company deals with adversity suggests how
well it will bring out the best ideas and talents of its people and
how effectively it will respond to change.”
—
Bill Gates, Microsoft
“Failure
is only the opportunity to begin again more intelligently.”
—
Henry Ford, Ford Motor Co.
“Remember,
Charlie Brown, you learn more from your defeats than your
victories.”
—
Lucy Van Pelt, Peanuts comic strip
The
day the line died
The
pathway to success isn’t always the smoothest. Gates dropped out of
Harvard. Ford’s first car company, Detroit Automobile, went belly up
in two years. Lucy struggled mightily as a rightfielder.
Spacesaver
Corporation hit its pothole in 2001. But the Fort Atkinson,
Wisconsin-based maker of high-density mobile storage systems used the
lesson to eventually find plant-floor success.
Spacesaver’s
productivity parable centers on Line 5, located in the fabrication
area of the 270,000-square-foot facility.
“Line
5 produces all of the shelf supports for our plant. It’s crucial to
our business,” says vice president of operations Jim Muth.
The
numbers don’t lie. The plant makes more than 6,000 shelves per day.
Each shelf requires two supports for the assembly process. Do the math
and Line 5 must produce in excess of 12,000 supports each day.
The
line had difficulties meeting the demand. It ran nights and weekends
to keep the parts flowing downstream. And then one day, in June 2001,
Line 5 flatlined.
“The
crash hit us right between the eyes,” says Muth.
According
to fabrication superintendent Marty Weber, air pressure issues, oil
leaks, a cracked ram shaft, a non-level ram and air cylinder wear and
tear contributed to the crash of the line’s main press. Looking
deeper, the existing production/maintenance philosophy left the line
vulnerable to such damage.
“We
were in a ‘run it until it dies’ mode, and it died,” says Weber.
“Because of product
demand, we neglected the equipment.”
The
machinery stopped. Demand for shelf supports, however, did not.
“Line
5 was down for several weeks,” says plant manager Michael Kling.
“Just like that we had to find outside suppliers that (combined)
could produce 12,000 shelf supports a day. It caused a substantial
amount of pain to get back on schedule.”
In
the aftermath, Spacesaver strongly considered tearing out the line’s
16-year-old machines and buying new equipment at a capital cost
approaching $1 million.
“It
would have been a major investment,” says Muth. “I didn’t want
to start a culture where buying new was the answer, the fix-all, when
the equipment got old.”
Following
Henry Ford’s footsteps, Spacesaver turned the crash into an
opportunity to begin again more intelligently. The
company found the smarter solution in a lean manufacturing technique
called Total Productive Maintenance (TPM).
Solution
was in front of us
Spacesaver
was no stranger to lean concepts. In 1998, the company was acquired by
KI (formerly Krueger International), a global furniture manufacturer
with a lengthy lean history, headquartered in Green Bay, Wis. In 1999,
Spacesaver adopted several lean principles and experimented with
kaizen events. The next year, it initiated a plant-wide value-stream
mapping project and completed 21 kaizen blitzes.
“The
solution was right in front of us,” says Muth. “When we had the
incident, the equipment on Line 5 was 16 years old. That’s not old.
But at the same time, we did 8,000 to 12,000 pieces per day for 16
years. That’s more than 40 million parts. If we would have made the
investment in new machines but treated it the way we did the current
line, we would have been right back at this point. What drove us to
TPM was its roots in lean.”
TPM
is an integrated set of activities aimed at maximizing equipment
effectiveness by involving everyone in all departments at all levels,
typically through small-group activities. TPM usually entails
implementing the 5-S system, measuring “the six big losses”
(equipment downtime, adjustments, minor stoppages, unplanned breaks,
time spent making reject product and waste), prioritizing problems and
applying problem solving with the goal of achieving zero breakdowns.
Spacesaver
sought advice from the Wisconsin Manufacturing Extension Partnership.
The talks confirmed TPM as the appropriate solution.
“With
TPM, we believed we could bring the equipment back to nearly like-new
condition,” says Muth.
How
TPM works
A
TPM project typically uses a modified kaizen format and can span
several months. It includes:
Training:
The company selects a team of people, including machine operators,
maintenance workers, supervisors and management. The process begins
with a day of training, simulations and case studies, plus instruction
on how to work in teams. The team also learns how to collect Overall
Equipment Effectiveness data (see sidebar). OEE is shop
floor-collectible data that documents how long a machine is actually
running, how long it’s down, how many reworks are needed, and so on.
OEE provides an easily applied and understandable way of measuring
machine utilization. It also serves as a record over time of a
machine’s performance and can be used as a reference guide for
future troubleshooting.
The
TPM team then decides which equipment to target first for improvement.
OEE
data collection:
During the next three weeks, the first OEE data is collected. This is
done by operators on all shifts. This serves as baseline data for the
project and shows where the problems lie.
OEE
data analysis/problem prioritization: The team meets to analyze the data and prioritize the
uncovered problems. The problems are categorized according to the
“six big losses” that reduce a machine’s efficiency. From there,
the root causes of these problems are targeted and corrected.
TPM
implementation:
Next, the team works to restore the equipment to make it as reliable
and productive as possible. Using the OEE data, high-failure-rate
areas are identified and the necessary repairs performed. Then, daily
and periodic maintenance schedules are established. A 5-S organization
and cleanup project is also part of the process.
To
document progress and improvement, the team continues to collect and
analyze OEE data from the equipment.
Bringing
TPM to Line 5
The
Line 5 TPM team consisted of team leader Weber, three Line 5 operators
(one from each shift), one operator from outside the area, a
maintenance mechanic, two engineers and a representative from
purchasing.
“This
project gave us the chance to take a step back and see how production
and maintenance functioned and what the consequences were for our
actions,” says mechanic and team member Bruce Campbell.
“From
maintenance’s perspective, we had a real problem getting access to
the line. Many times, we were asked to put a Band-Aid on a machine
just to get it back up until the weekend. Then on Sunday, we could
come in and do what we had to do to fix it right. However, if the
production output on Line 5 was low, the operators would have to work
on Saturday and Sunday. The fix then would be scheduled two weeks out.
It wasn’t the right thing to do. But from the operators’
perspective, they needed the machine so they could get parts out.”
What
is more important: parts production or equipment maintenance?
Spacesaver pondered that chicken-and-egg conundrum and decided
that “both” was the correct choice.
Utilizing
one of the tools of TPM, plant leaders reassigned a host of routine
maintenance tasks to machine operators. In essence, operators were
given joint custody of the equipment.
“Operators
used to insinuate that maintenance couldn’t keep the machines up and
running. Maintenance would insinuate that operators weren’t running
the machines correctly,” says Weber. “Joint ownership helped put
everyone on the same page.”
Adds Muth, “It’s now everyone’s job to ensure that this machine runs
as efficient and productive as possible. The operator should have as
much accountability and responsibility as maintenance does.”
Operators
received training as well as a daily checklist of preventive
maintenance tasks. The list includes checks for fluid levels, tool and
die condition, and oil and air leaks, and examinations of pressure and
thermal indicators. It also includes machine cleaning activities.
“They
go through a running PM,” says Campbell. “The operator checks the
machine out for certain issues. That person can address the minor
issues. If anything larger in scope needs addressing, the supervisor
generates a work order and we take care of it. This allows for more
proactive work rather than waiting for someone to say, ‘It broke
because it ran out of oil.’”
Maintenance
relinquished some of its control in the area of asset health but, in
doing so, found that its time and skills were better utilized.
“We
didn’t have a problem handing off our knowledge to the operators,”
says Campbell. “I can fill oil. I can do all of the small stuff. But
with the knowledge and skills I bring, I’m better off focusing on
bigger issues. We now can get into projects rather than
firefighting.”
Examples
of maintenance’s shift from reactive to proactive work includes
expanded use of infrared analysis and other predictive tools,
experiments into oil analysis and the creation of a “fourth shift”
that handles advanced PM tasks on Saturdays, Sundays and Mondays.
A
byproduct of the arrangement has been greater understanding and
teamwork between the two groups.
“When
TPM occurred and we increased our production numbers so drastically,
it wasn’t as big of a deal for me to say, ‘I need the line for six
hours in order to fix this the proper way,’” says Campbell.
“There will always be capacity issues because we are a lean
manufacturer and we don’t build the inventory up. However, we do
have the capability to build things up so we can take the machine down
for six hours.”
Getting
results
The
TPM project led to many action items for Line 5 outside of operator
checklists and proactive maintenance. These include:
ACTION
ITEM #1
Square
and level the press.
Goals:
Make certain the press ram operates level; eliminate undue wear to the
slides and gibbs of the press; ensure part quality is consistent from
start to finish; and, avoid stress cracks in the press frame.
Results:
Spacesaver contracted an outside firm to level and square the press;
during the firm’s visits, maintenance rewelded the stress cracks in
the frame.
ACTION
ITEM #2
Capture
leaks.
Goals:
Review the entire line for leaks around fittings, caps, cylinders,
seals and tubes.
Results:
Numerous tubes, pipes and fittings were replaced. Catch basins and
drainage tubes were also installed to catch overspray of coolant and
excess oil.
ACTION
ITEM #3
Totally
rebuild the air manifold system.
Goals:
Eliminate all leaks; reduce the number of air controls by 50 percent;
and, refurbish or upgrade the air cylinders to newer technology.
Results:
The entire air system for tooling was refurbished to reduce the number
of controls from 16 to eight. Also, the existing cylinders were
reworked with new bushings that eliminated leaks. Finally, the
controls were relocated to an area protected from the elements.
ACTION
ITEM #4
Redesign
the transfer conveyor between the press and the riveter.
Goals:
Gain access to the back of the press for working on tooling; eliminate
downtime due to problems with the transfer system; and, eliminate
personnel standing on the conveyors in order to gain access to the top
of the press.
Results:
The conveyor and tooling was modified to easily swing out of the way.
This provided greater access to the rear of the press for both
maintenance on the tooling and the top of the press.
Easing
the pain
Everyone
faces adversity and tough decisions on the road to achievement. How
you handle it determines your ultimate success.
After
dropping out of Harvard, Bill Gates helped start a little company
called Microsoft. After Detroit Automobile tanked, Henry Ford created
the Ford Motor Company. And on April 21, 1994, after more than 40
comic-strip years of trying, Lucy Van Pelt caught a fly ball and gave
Charlie Brown’s hard-luck baseball team a victory.
“We
had to have the pain before we saw things clearly,” says Muth. “It
just so happened that our pain hit us during the busiest part of our
business and in one of the most critical areas of the plant.”
Spacesaver
handled the pain on Line 5.
“Because
of our work, I’d say 30 to 40 percent of downtime has been
eliminated,” says Weber. “Overtime is under control. If we do work
a Saturday or Sunday, it’s because of the workload, not because of
an equipment breakdown.”
Recently,
the company has spread TPM and other lean techniques to other areas of
the plant. Such improvements were critical as business increased
substantially.
“The
business has grown 60 percent in recent years without adding brick and
mortar. And, we still have room to grow,” says plant manager Kling.
A
large-scale business jump and a more productive plant?
Now that’s turning peanuts into peanut butter.
This article
appeared in the April/May 2005 issue of MRO Today magazine.
Copyright 2005.
Back to top
Back to Cover stories archives
|