|
Ranger
rides a new wave
Ranger Boats are
revered throughout the sport fishing world, but they aren’t just
floating on that reputation. Seems you can teach an old bass
new tricks.
by Tom Hammel
Fishing has come a long
way from a pole, a hook and a worm on the riverbank. It is a highly
competitive, individualized sport peopled by men and women who share
a passion for the lifestyle, who take great pride in their equipment
and who express their personalities in their boats.
With its rich heritage
in the sport fishing world, and its happy location just three miles
from the White River, one of America’s premier angling rivers, and a
stone’s throw from some of the country’s finest bass lakes, few
companies understand their customers as well as Ranger. Each angler
is different, and each angler’s needs are different. So Ranger
doesn’t just meet customers midstream—it goes all the way across.
“Every Ranger Boat is
built to order; we don’t build to spec,” says S. Keith Daffron,
Ranger’s vice president of sales. “We have 40 different base models,
but with all the variations in models, colors and equipment, the
possible combinations run into an infinite number. And in many
cases, they add up to a $50,000 bass boat.”
That’s serious fishin’
right there.
One at a time, times
18
The way Ranger meets this highly individualized demand is by
building boats literally from the inside out, one at a time, in a
continuous flow with just-in-time delivery of customized
subassemblies.
“We build our products
on open molds on casters so we can roll them through the process,”
he explains. “Our flexibility is built into our mold capacity, so we
can take one mold out, insert a different model and build that boat
because it is with its mold for three days. The laminate cures in
that mold until the third day when we pull it and mate the hull with
its deck. Then we can reuse that mold the next day for another boat.
“But it’s not like a
person would envision where we batch build. It doesn’t work that way
here.”
Ranger produces about
5,000 boats a year this way, roughly 18 each day in what can only be
called a low-volume, very-high-mix process.
Today, retail customers
typically use Ranger’s online “Build your own boat” design program
to choose color schemes and equipment as they build their orders. In
“the old days,” it was all done at a dealership with fiberglass
color samples and catalogs.
Smile! You’re in
Flippin!
Set on 40 acres in the town of Flippin (population 1,253) in
northern Arkansas’ lush Ozark Mountains, Ranger now occupies 500,000
square feet of manufacturing and support space in two adjacent
plants. Plant 1 operations include subassemblies such as boxes and
lids for storage and live well areas on the boats, carpeting, seats
and upholstery and pultruded fiberglass components for transoms and
stiffeners. These Plant 1 operations feed Plant 2, where assembly
takes place.
Ranger boats are
essentially two-piece fiberglass shells that are spray laminated,
layer by layer, on mated molds. These molds, one deck and one hull,
flow through production in parallel until they ultimately come
together to form one piece. Decks are built upside down; hulls are
formed right side up. As they sit on dollies on the floor, deck
molds look like brightly colored, crudely shaped battleship forms
with various levels of deck surfaces and a central bridge at the
top. However, what appears to be the roof of the ship’s bridge is
actually the underside of the bottom of the boat’s passenger well.
For the 3-D-challenged, it’s a bit of a trick to learn to see the
boat’s true contours at this stage.
But this upside down,
inside out logic is perfectly suited to construction. The exposed
deck “surface” allows operators full access for installing
electrical and plumbing line chases, boxes and other components that
will be hidden in the boat’s innards when the deck is finally
de-molded and flipped right side up to mate with its hull.
The molds travel with
the decks and hulls until the last minute before they are mated.
From first spray to final de-molding, this takes three days, so at
any point in time there are three day’s worth of boats in some stage
of construction in the plant. This three-day inventory drives every
subassembly process in the plant, from seats and consoles to wiring
harnesses, boxes, lids and trailers. Because customers want their
boats and trailers to match, few Ranger boats are built without a
color-matched trailer. Hell, the trailers alone are gorgeous.
The hulls, formed right
side up, also receive subassemblies including their transoms and
stiffeners from the pultrusion shop. To meet demand, the pultrusion
shop runs on a three-shift schedule, five days a week. Most other
areas of the plant operate on a single-shift workday, although some
of these, including maintenance, are staggered between first and
second shift. Some subassembly operations, such as installing
transoms and stiffeners in boat hulls, are done on second shift to
prepare for the next day’s final assembly processes.
Finally, the hull and
deck halves “snap” together like a plastic model car body snaps onto
its finished chassis. And, as in model cars, this joinery process
includes a high-strength adhesive that is carefully applied to every
point where hull meets deck to add rigidity and eliminate air voids
from the finished structure. Of course, with a full-sized boat,
there’s a bit more glue involved.
Smooth flowing,
straight shooting
For a plant this size, the maintenance staff is surprisingly small,
just 12 in total, including three mechanics to maintain the
company’s fleet of 18 trucks. The plant maintenance staff numbers
five people, who specialize in various areas of critical demand such
as electrical, plumbing, hydraulics, HVAC and pumps. Maintenance
here frequently involves pumps.
“We have several
hydraulic systems in the pultrusion area and the trailer shop, the
areas where we have most of our heavy equipment,” explains Dan
Heiskell, plant manager. “However, most most of our PMs are centered
around our pump systems supporting our gel coat and chopper gun
areas.”
Chopper guns spray a
“chopped” fiberglass filament and resin mix onto the hull and deck
forms. The resin they shoot demands they be maintained daily, a job
that falls to their operators. Ranger contracts its housekeeping
maintenance to a third party provider and trains its equipment
operators on daily maintenance of their equipment. These steps have
helped reduce the demand on Ranger’s existing maintenance staff.
“To be honest, there
aren’t many mechanical systems in the boat-building part of the
process that have to be maintained daily by our maintenance staff,”
Heiskell says. “Much of the daily maintenance is done
interdepartmentally operators are responsible for their own daily
cleanup and checks. This is why we have such a small maintenance
staff. First, there’s not a lot of equipment to break down, and
second, if the operator is doing the daily gun cleaning and we’re
doing the proper PMs, there’s not a high level of maintenance
required.”
The boat decks and hulls
are pulled around the plant by motor-driven conveyors, and any
issues with them must be addressed immediately to keep the plant
moving. That means conveyor issues are a top priority. Motorized
conveyors are also used in other operations, such as the box and lid
department.
Larger and leaner
As Ranger grows, it increasingly takes advantage of its annual
shutdown week in July not just for yearly maintenance and new model
changeovers, but also for systems upgrades and capacity expansions.
This year Ranger took two weeks to make all the improvements. Lean
tools and processes are at play in every systems upgrade.
One of these upgrades in
particular has employees cheering. Ventilation systems are critical,
especially to the proper curing of deck and hull laminates. Add this
to the sweaty fact that temperatures here can hit the mid-90s in
early June, keeping workers from overheating is important, too.
Maintenance is systematically pulling out pedestal floor fans and
replacing them with air conditioning. What’s so Lean about air
conditioning? Not only is energy consumption going down, work areas
are much cooler, quieter and safer to boot.
The gel coat area is
heat sensitive too, and must be maintained at 85 F. This area was
also expanded in the July shutdown. “We rearranged our whole gel
coat area to accommodate 12 spray booths,” Heiskell explains. “We’re
spraying more stripes and patterns onto the boats and we need more
space to do it.”
In both decks and hulls,
the first layer to be sprayed is the gel coat body color. Customers
can select color packages that may require as many as 16 different
spray cycles, each of which must be taped off, sprayed and given 20
minutes to cure before the next color can be added. It takes time to
realize a customer’s vision of the perfect boat.
Similar initiatives are
taking place in the box and lid area, where a cell designed around a
mold carousel allows workers to make box lids via closed cavity
molding in a space less than 20 by 20 feet, with minimal worker
movement required between production steps. As one lid is de-molded,
its silicone mold goes back onto the carousel, which carries it
around to the fabrication side of the cell in time to be grabbed and
used again for the next lid.
Molds on the carousel
are coordinated to the day’s boats in process. It works well: this
small area produces 200 lids and 100 boxes each day.
This use of Lean tools
carries right on through to the finish room. The plant’s wiring shop
occupies a cell directly adjacent to the stations where wiring
harnesses are installed in the boats. The wiring cell produces all
the harnesses needed for the next day’s orders. When completed, the
harnesses are kitted together, tested and rolled over to the
assembly area in bins. Visual instructions aid wire workers in
making up different harnesses. Circuit breaker arrays are now
pre-mounted on boards that are then installed on the boats, saving
time.
“Premounting our
breakers is also a new Lean initiative,” Heiskell says. “An offline
operator mounts these on a board that is ready to go straight into
the boat. “We check every wire harness before it goes into the boat
so we don’t have any issues after it is installed.”
Console assembly is also
being “Leaned.” Consoles used to be installed on the boats and then
wired with instruments and cables. Now they are prewired adjacent to
their installation bay, gauges and instruments are fitted, leaving
only simple connections to be made when the console is attached to
the boat. Just-in-time wiring.
“The console is an
add-on piece so we can kit it up — assemble everything on it, bring
it to the boat and just put it on,” Heiskell says. “Before we would
have to crawl under the console to make connections and it was a
very difficult place to reach. That step alone has saved us 20
minutes of assembly time per boat.”
A major time and floor
space saver has been the installation of a monorail conveyor system
for boat motors in a warehouse adjacent to final assembly. The
warehouse area will hold 800 motors. A new overhead rail by ABB
Crane Systems allows easy offloading, storage, staging and
just-in-time delivery of motors to final assembly just yards away.
This motor warehousing
solution has freed up much-needed floor space, allowing final
assembly to expand from four lines to five. This has had immediate
benefits over and above “just” added capacity.
“Before, we had 14
models running down one line,” Heiskell says. “Our workers had to
know how to assemble 14 different models with umpteen different
options. Splitting the line into two lines with 7 models each has
made the learning curve much shorter, as well as increasing our
capacity.”
When the completed boats
roll off the line, hoists lift them into a dunk tank for a wet test
of all components. Then the boats are wiped down, shrink-wrapped for
shipping and rolled out the back door. From here they are loaded
onto trailers for delivery to their eager owners.
Back inside the finish
room, another boat rolls off the line. The afternoon sun dances on
its ruby hull, flashing off the metal flake finish as if the boat is
already on water.
They sure are beautiful,
we observe. “Yes they are,” Heiskell agrees. “Everybody should have
two of them.”
|
1.
The first thing that goes into building a Ranger boat is the
first thing you see when you look at one, the finish. Here a worker
sprays gel coat finish into a boat hull mold while another one cures
in the foreground. Each color must be individually taped off,
sprayed and cured for 20 minutes at 85 degrees before taping can
begin for the next color.
2.
Because the finish is applied directly onto the hull mold, the
interior surface of the mold must be maintained in a highly polished
state to ensure a blemish-free finish. Each mold is thoroughly
inspected before each use. During the build process, each mold
travels with and supports its laminate structure for three days.
3.
Awaiting their next use, deck molds look like simple ship models
with multilevel decks and bridge towers, but what you see is
actually the the underside of a boat deck mold. The tallest area is
the passenger well and the elevated rectangles will become recessed
box portals.
4.
This deck mold has been sprayed up and is curing. On the next
shift, workers will install wiring and plumbing chases and partially
lift the deck away from the mold for a first inspection of the
glossy finish hidden beneath. The rail system overhead tows the
wheeled mold from one station to the next. Tomorrow, this will be a
finished boat.
5.
The wire shop in the finish room is located next to the assembly
stations where the harnesses are installed. The harnesses made by
the wire shop today will go into boats tomorrow; the shop is never
more than one day ahead of final assembly. The diagram (inset) shows
instructions for a breaker subassembly that will be mounted here in
the shop, tested and taken out to assembly.
6.
Finally, the hull and deck are joined and the end of the line,
the back door to the boat yard, is literally in sight. On this, the
first of four final assembly stations, two workers are wiring the
boat and connecting the plumbing lines. In later operations the box
lids will be installed, the motor will be attached and a final
cosmetic inspection and buffing will be completed. The seats go in
last. The five assembly lines are balanced so each boat will move to
the next step in 45 minutes.
|
This
article appeared in the August/September 2007 issue of
MRO Today
magazine. Copyright 2007.
back to top
Back to Cover
stories archives
|